Tomoka River Bridge Photo's

Click on a picture for a larger version. Lower resolution pictures were used in order to speed up download times. Higher resolution pictures are available.

Pictures Overhead 5/20/99 (Look Below)        First Test Pile Driven 12/21/99 (Look Below)

Last Test Pile Driven 1/06/00 (Look Below)     Begin Bridge Demo 1/11/00 (Look Below)

Beam Setting Photos (Click Here, photos not on this page)

Aerial Photos and 1956 Photo 5/26/00 (Click Here, photos not on this page)

Pour Deck 5/6/2000 (Click Here, photos not on this page)

Pour Deck 8/11/2000 (Click Here, photos not on this page)

Pour Barrier Wall 9/5/2000 (Click Here, photos not on this page)

Profile Bridge Deck and photos of House Moving across bridge (9/18/00)
(Click Here, photos not on this page)

Demolition of southbound bridge  and photos of new northbound bridge (10/26/00)
(Click Here, photos not on this page)

Pouring New Southbound Bridge Deck and Demolition of the Old Bridge (01-/31/01)
(Click Here, photos not on this page)

Construction photos from January and February 2001
(Click Here, photos not on this page)

Construction photos from March and April 2001
(Click Here, photos not on this page)

Construction photos from May 2001
(Click Here, photos not on this page)

 

wpe26.jpg (39845 bytes)    wpe28.jpg (43761 bytes)   wpe2A.jpg (42995 bytes)   wpe2C.jpg (37532 bytes)

Overhead views of the project before construction began.

Bridge Project Test Piles 12/21/99 - During Construction

 
Test Pile in Frame. Frame is used to hold the Pile in Place before the Hammer
gets on it.

   
Test Pile in Frame

   
Pile Leads which holds the hammer getting ready to be placed on the pile


Hammer on the top of the pile before driving.

 
PDA (Pile Driver Analyzer used  to determine the capacity and length of the piles for the project.)

Last Test Pile 1/06/00

Test Pile-1.jpg (41357 bytes)
Hammer on Pile

Test Pile-1b.jpg (39053 bytes)
Close Up

Tommy1.jpg (57356 bytes)
Tommy (Pile Driving Inspector) running the saximeter.  The saximeter gives the blow count per foot and how high the hammer is dropping (4-10ft).

Jeremy-Gordon.jpg (240505 bytes)
Gordon and Jeremy (Geo- technical Engineers) the Pile Driving "Gurus" using the PDA to find out how deep to drive the piles.  Gauges run from the pile to the PDA feeding it info on stresses and strains the hammer is producing on the pile. They determined the piles need to be between 31 and 48 feet long for the project.


Begin Bridge Demo

    

demospan11d.jpg (19931 bytes)  demospan11c.jpg (20315 bytes)  demospan11b.jpg (20697 bytes)  demospan11a.jpg (19905 bytes)  demospan11.jpg (18826 bytes)

Demolition of Span 11. One span at a time will be demolished.  After each span is demolished a new span will be built in its place. This is being done so the existing bridge can be used as a platform to build the new bridge.  That way a large barge with a crane on it is not needed in the river.

 

Questions on the Tomoka River Bridge Project
Email: [email protected]
Phone: 904-677-8740
Fax: 904-677-2940