Ready to pour first section of bridge deck 5/4/2000

Click on thumbnail for larger picture

BidWell.jpg (44179 bytes) Overhang and Screed.jpg (37012 bytes) span 7 steel a.jpg (55130 bytes)

This machine, made by the BidWell Company, moves along the surface of the bridge grading and compacting the wet concrete.

5/7/2000

The concrete is being placed in the photos below

 

 Deck pour span 5a.jpg (54040 bytes) Deck pour span 5e.jpg (42912 bytes) Deck pour span 5f.jpg (45697 bytes)

Here the crew from Russell Engineering is placing the fresh concrete while the BidWell machine ( the yellow structure) finishes it smooth.

 

 

 Deck pour span 7.jpg (34938 bytes) Deck pour spn 6.jpg (29743 bytes)

Views from the Tomoka Boat Club looking west at the bridge. The boom of the concrete pumping truck is visible on the photo on the right.  This machine takes the concrete from the concrete truck and pumps it onto the bridge.