Links
Deck Launching System
(New page added 8-10-03)
Update
structurae: Millau Viaduct
A75 -
La Méridienne: Viaduc de Millau
Aurelle-Verlac: Viaduc de Millau
Chantier du Viaduc de Millau (visite virtuelle)
Eiffage: Le Viaduc de Millau
Enerpac: Millau Viaduct, France – The world’s highest bridge
Foster and Partners: Millau Viaduct
Le Moniteur BTP: Début du lançage du tablier du viaduc de Millau
(26.02.2003)
Millau-Clic: Le viaduc sur la voie d'une ouverture pour juillet
2004
Millau-Clic: Viaduc de Millau: Historique d'un projet né en 1987
OTUA: Viaduc de Millau
Pour une alternative au Viaduc de Millau
Viaduc
de Millau
Viaduc de Millau (official site of the concessionaire)
Yahoo! France: Grand Viaduc de Millau
PERI
Formwork and Scaffolding: Viaduc de Millau, France
|
PROJECT OVERVIEW
This Cable-Stayed Bridge Project is on schedule to be completed
January 2005. (39 month construction contract). This
project is being financed privately. This project has the
highest bridge piers in world. Thus the title of the
Highest Bridge in the World. The tallest will be 240 meters
high. Overall height an outstanding 336.4 meters. This project
will consist of seven separate cable-stays.
Bridges are often considered to belong to the
engineer's realm rather than the architect's. But the
architecture of infrastructure has a powerful impact on the
environment. The Millau Viaduct, designed in collaboration with
engineers, illustrates how the architect can play an integral
role in bridge design.
Located in southern France, the bridge will connect the motorway
from Paris to Barcelona at the point where it is interrupted by
the River Tarn, which runs through a wide gorge between two
plateaus. A reading of the topography suggested two possible
approaches: to cross the river, the geological generator of the
landscape; or there was the challenge of spanning the 2.5
kilometers from one plateau to the other in the most economical
manner.
The structural solution follows from the latter philosophical
standpoint. The bridge has the optimum span between cable-stayed
columns. It is delicate, transparent, and uses the minimum
material, which makes it less costly to construct. Each of its
sections spans 350 meters and its columns range in height from
75 meters to 235 meters - higher than the Eiffel Tower - with
the masts rising a further 90 meters above the road deck. To
accommodate the expansion and contraction of the concrete deck,
each column splits into two thinner, more flexible columns below
the roadway, forming an A-frame above deck level. This structure
creates a dramatic silhouette - and crucially it makes the
minimum intervention in the landscape.
Construction Date: 2001
Completion Date: 2005
Statistics: Length: 2.5 km
Height: 280 m (Above information provided by
Foster and Partners) Architectural Design:
Foster and Partners
Design Concept: SETRA
Structural Engineering:
EEG Simecsol and
Greisch
Contractor:
Eiffage Construction
Co-Contractor: Eiffel
Construction
Fabricator: Freyssinet
(stay cables)
Launching Enerpac
Formwork: PERI
Formwork and Scaffolding UPDATE
| 16 October 2001 |
Beginning of construction |
| November 2002 |
Pier P2 (to be the highest)
reaches 100 meters in height. |
| 26 February 2003 |
Launching of the deck
commences. |
| January 2005 |
Expected opening |
Click on pictures for larger versions.
 The
world´s highest bridge piers (245 m) will be constructed using
PERI formwork and climbing technology. The 2,460 m long motorway
viaduct near Millau in south France is the area upon which this
construction will take place. (Photo: PERI GmbH)
 PERI´s
solution of having only one anchor position in the concrete (2nd
position above the concrete joint) up to 4 metre high concrete
sections, reduces both shuttering time and presents a 50 %
reduction in required anchors. The steel formwork provided a
solution that met the stringent demands concerning architectural
concrete. (Photo: PERI GmbH)

Single-shafted
piers: The working platforms can be adjusted according to the
varying cross sections of the pier, in order to provide a safe
working condition for all personnel. (Photo: PERI GmbH)
|
Millau Viaduct, France – The world’s highest bridge |
 |
A great new
work of French Structural Engineering and
Spanish/American Hydraulic Technology.
In June l2001 Enerpac (Hydraulic
Technology) was awarded the contract to supply the
hydraulic system for lifting the temporary piers and
pushing the bridge decks for the Millau Viaduct Project.
Today, the works are in full process and history is
being written whilst we speak: The world’s highest
bridge is being build.
The bridge decks for the Millau Viaduct
Project.
After considering various route options, on 28th June
1989 CETE (the Center for Technical Equipment Studies1)
of Aix-en-Provence selected the 'middle' route running
to the east of Millau over the River Tarn. This 'high
solution', included a great viaduct, which would 'soar'
over the Tarn valley without descending into it, thus
avoiding the necessity for a tunnel. This has been the
preferred option since 1991 because it scarcely affects
the environment and offers better safety than the other
option. The detailed studies commenced in 1993 and in
1994 the restricted competition was called, in which
five teams of architects participated, the winning
alternative being that submitted by the team comprising
French engineers Sogelerg, EEG, SERF and Foster, in
1996.
The studies for the Millau Viaduct
started back in 1988 with the objective of ending
congestion on the A75, the motorway link between Paris
and Barcelona.
From design to construction
Foster's design, impressive due to its aesthetics and
size, was not exactly easy to construct without getting
into cost difficulties. Supported by two abutments and
seven piers, it flies the 2460 m above the Tarn valley
at a central height of 245 m, with 204 m spans between
the abutments and the first and last piers, and 342 m
spans between the remaining piers, the heights of which
range from 70 m for the first and 340 m for the third
pier. The structure is multi-stayed with vertical hollow
concrete members in the shape of tuning forks which
support the two carriageways from the center, the
carriageways having a total width of 27.35 m, sufficient
for three lanes in each direction (of which only two
will be put into service at the beginning) and hard
shoulders on both sides.
From the driver's point of view, the viaduct has a
gentle slope (3.035 % from north to south) and a gentle
curve (radius 20 000 m). It is 270 m above ground level
in the middle, although the central pier with its stays
exceeds 340 m in height, meaning that it is 14 % taller
than the Eiffel Tower.
Two types of deck were investigated, of concrete or of
steel, the latter being decided on as it would be
slimmer which not only leads to better aesthetics (the
concrete deck would have required a height of 4.6 m),
but also to greater safety, both during the period of
construction and in service.
27 000 cubic meters of concrete, 19 000 tonnes of
concrete-reinforcing steel, and 5000 tonnes of
reinforcing steel for cables and coverings were required
for its construction. It was decided to use B60
high-specification concrete for the piers and
self-climbing metal shuttering of variableshape.
Once the decision of the final configuration of the
works had been made on 9th July 1996, it remained to
determine who would execute it and how. Several
companies participated in the competition for the
concession, however the French Department of Transport
and Public Works opted for the Eiffage Group TP (third
in size in France and fifth in Europe), which created a
company specifically for its operation, the Compagnie
Eiffage du viaduc de Millau. This company was awarded a
75-year operating concession in exchange for financing
the works, whose cost was estimated (at the commencement
of construction) at €300 000 000, plus a further €20 000
000 for the toll station located 6 km further north.
The works has been designed to withstand the most
extreme seismic and meteorological conditions, its
faultless operation being guaranteed for at least 120
years. The greatest constructional problems lie in the
building of the deck, with a mass of 36 000 tonnes and
which will be pushed out from both ends. The elements
will be prefabricated at the Eiffel, Lauterbourg and
Fos-sur-Mer sites, and an assembly of 64 hydraulic jacks
will be used for pushing. The 'travel' involved in each
of the six central spans, 342 m, made the installation
of five temporary piers necessary, for the construction
of which the Spanish division of Enerpac was turned to.
Hydraulic system lifts intermediate temporary piers
Seven intermediate temporary piers are
required between the definitive piers in order to
'launch' the deck.
When the Millau Viaduct was being designed, Eiffel, a
subsidiary of the Eiffage Group and dedicated to steel
construction, estimated that seven intermediate
temporary piers were required between the definitive
piers in order to be able to 'launch' the deck during
its construction.
Once a pier has been raised the machinery including the
hydraulic system, is disassembled and moved to the
location for installation of the following pier
Information kindly provided by Enerpac.
Enerpac Hydraulic System Integration
for Millau Viaduct
Pushing the 4000 ton deck
out into space - Check
out how the deck is launched! |
|
|
|