West Busway
The Port Authority has completed building a fourth busway. The $326.8 million total project, which started with the groundbreaking ceremony on October 27, 1994, connects downtown Pittsburgh with the western Allegheny County neighborhoods and the Pittsburgh International Airport corridor.
|
The most challenging aspect of the project was the refurbishing of the 148 year old Barry Street Tunnel, a former rail tunnel, that carry the buses between Sheraden and Ingram. The restoration began in December 1995 and lasted until 1997 at a cost of $33.3 million. Some of the work that took place was widening the tunnel to accommodate two lanes of traffic, excavating the existing brick lining, and installing tunnel lighting, ventilation, fire protection, and drainage. |
Construction of busway ramps connecting to the Parkway West near Carnegie and Rosslyn Farms began in mid-1998. The Corliss Flyover, which will connect the busway to West Carson Street, began in March 1999. Construction of the mainline was completed in September 2000 when the Parkway West interchange and Corliss Flyover were completed.
On September 8, 2000 the first segment from Carnegie to the Corliss Flyover opened. With the opening came a new bus route: 100 West Busway. No personal vehicles can use this highway; however, it will be open to emergency vehicles. Buses using the new route can cut 26 minutes off the same trip via the Parkway.
The mainline busway runs between Pittsburgh and the Borough of Carnegie, with a connection to West Carson Street and the Parkway West. Direct access to Carnegie, Crafton, East Carnegie, Ingram, and Sheraden is provided. The busway reduces travel times by avoiding the congestion on the Penn-Lincoln Parkway, and speeding the nearly 40,000 daily riders to the designations quickly.
Another part of the project is the renovation of the Wabash Tunnel. The 1.1 mile tunnel, which runs between PA 51 and Station Square, has been reconstructed at a cost of $3 million to accommodate two lanes of traffic. It was built at the turn of the century to carry the Wabash Railroad through Mt. Washington to its terminal in downtown Pittsburgh. This was the tunnel that was abandoned by the County of Allegheny that was to be used by the SkyBus system, an early form of a monorail. The piers for that bridge still remain at Stanwix Street and at the Gateway Clipper boat docks at Station Square.
Most of the discussion of this project lies in the alignment of a new bridge on those old piers. Some of the proposals have the bridge coming into Pittsburgh above the current street grid. A plan that former mayor Sophie Masloff liked was to have the bridge meet Stanwix using the current piers and would also call for the lowering of the Parkway East's eastbound lanes. All traffic will be able to use the bridge, which would have connections with downtown, Carson Street, and the Wabash HOV facility. Project website: http://www.portauthority.org/grow/capital/monriver/index.asp.
Links:
West Busway Map
Port Authority of
Allegheny County
West
Busway - Port Authority of Allegheny County
Wabash
Tunnel - Bruce Cridlebaugh
INFORMATION |
|
| Western Terminus: |
Campbells Run Road in Carnegie. |
| Eastern Terminus: |
West Carson Street in Pittsburgh. |
| Length: | 5 miles |
| Name: | West Busway |
| Emergency: | 911 (412) 255-1350 (Port Authority Police) |
| Area Codes: | 412/878 |