US 322
Twenty-Eighth Division Highway


This highway connects the northwestern and southeastern sections of Pennsylvania with the state capital of Harrisburg.  In the early days, the highway traversed Meadville on Mercer Street, Water Street, Poplar Street, and Liberty Street and in Franklin on Grant Street, 13th Street, Liberty Street, and 8th Street.  The original route of US 322 has not changed much except for two areas:  Grapian to Clearfield where it used to follow current PA 879 and from Phillipsburg to Bald Eagle where it followed current PA 970 and PA 350.  It continued onto Water Street via Business US 220, PA 453, and PA 45 and ended at US 22.  In 1929, the highway was still unimproved from the Ohio state line to Hartstown.

In 1933, the designation was moved to the current alignment from Phillipsburg to Port Matilda and extended to end at Lewistown.  In State College, the designation followed Atherton Street.  In 1934, the highway was under construction to improve it from the Ohio state line to Jamestown.  In 1935, the rebuilding of the highway from the Ohio state line to Jamestown was completed.  In 1936, the designation was extended again to Harrisburg and onto Chester via the current alignment.  In Harrisburg, the designation followed River Road, Front Street, and Paxton Street and in Chester Concord Avenue and Flower Street.  The same year the highway was finished from Jamestown to Hartstown.  The final year of the 1930s saw the beginning of several widening projects to provide safer travel along the highway.  The first sections to see work were from Lewistown to Mifflintown, Speeceville to west of Dauphin, PA 443 to Harrisburg, Harrisburg to Hummelstown, and US 202 to Concordville.

The 1940s began with widening taking place from US 19 to one mile west of Kerrtown, Kerrtown to Meadville, west and east of Franklin, Burnham to Lewistown, the Centre County line to five miles inside Mifflin County.  Work stopped during World War II, but began again in 1945 with the section from Martha Furnace to near Buffalo Run and Speeceville to Dauphin widened.  In 1949, the widening that was performed in 1940 was extended inside Mifflin County to near the town of Milroy and the section from Clarks Ferry to Speeceville was also widened.  That same year, construction began on a new alignment from Concordville to Chester.

In 1950, widening continued with a section from Amity Hall to the Clarks Ferry Bridge seeing work.  In 1951, the new alignment of US 322 opened from Concordville to PA 452; however, the designation remained on the former route.  The following year, the highway was widened from Dauphin to PA 443 and from US 19 all the way to Meadville.  In 1953, the highway was widened from Clarion Junction to Clarion and from Pottersville to Lewistown.  Construction began that year on the Hummelstown bypass which opened 1954.  The year 1954 saw a lot of developments take place.  The first was the highway was widened in a section west of State College, from west of State College to PA 550, and Yeagertown to Lewistown.  The second was changes of the alignment in Meadville where the designation was moved to Park Avenue, and placed on the alignment from PA 452 to Chester that opened in 1951.  Construction also a story on the highway that year, as work began on the West Chester Bypass, which opened the following year.  The section of the bypass from west of town to where US 202 connects is a "Super 2," with plans to have constructed another set of lanes which was never done.  In 1956, the highway was widened in Grapian, and from Milroy to Yeagertown. In 1958, work to divide the highway began with the first sections from US 19 to Meadville, south of Meadville to the intersection of Poplar Street, east of Curwensville, west of State College, Speeceville to Amity Hall, in Dauphin, Eisenhower Boulevard to US 422, and from Lincoln to Ephrata seeing the first projects completed.  Also that same year, work to widen the highway was performed in Cochranton, over Clearfield Creek, west of Reynoldsburg, in Clearfield, in Honey Brook, and in West Chester.  In Harrisburg, the designation's westbound route was changed to follow Second Street and Division Street and construction of the Lewistown bypass commenced.  The northern section of the West Chester bypass opened and provided travelers a non-stop route around the town.  In 1959, the highway was widened in Phillipsburg and west of Woodland.  The highway was divided from the West Chester Bypass to US 1.  The US 322 designation was moved to Linden Street in Meadville this year.  While the Lewistown Bypass opened to traffic, work began on another section.  Construction began on Interstate 83 from Second Street to Eisenhower Boulevard.

In the first year of the 1960s, the US 322 designation was moved to the Lewistown Bypass.  Also that same year, the Second Street interchange of I-83 opened to traffic.  In 1961, the highway was divided from Conneaut Lake to US 19.  That same year, I-83 opened to traffic from Second Street to Eisenhower Boulevard.  A lot of work took place along the highway in 1962.  Construction began on a new alignment from Cochranton to Hannasville and on the Cornwall Bypass.  Dividing projects took place from west of Boalsburg at PA 45 and from US 202 to Concordville.  The highway was also widened in Wallaceton and the I-95 interchange at Flower Street opened to traffic.  In 1963, the new alignment from Cochranton to Hannasville opened to traffic as did the Cornwall Bypass.  That same year, the US 322 designation was moved onto I-83 from Second Street to Eisenhower Boulevard.  Also in 1963, the Department of Highways planned to build the Conchester Expressway from I-95 to US 1 and onto the proposed, and never built, US 202 expressway.  The plan was scrapped in 1974, and the only evidence of this project is the section of expressway west of Interstate 95.  Construction began in 1964 on new sections of expressway from south of Milroy to the Burnham-Lewistown Exit and from Newport to Amity Hall.  That same year, the designation was moved onto the West Chester Bypass.  In 1965, the expressway opened from south of Milroy to the Lewistown Bypass and from the Newport Exit to Amity Hall.  Construction began on the section from northeast of Newport to the Newport Exit and to upgrade US 322 to expressway standards for I-95 from Exit 3 to Exit 4 that same year.  In 1966, work began on a new alignment from just south of the Centre County line to Milroy and from the Juniata County line to Newport.  In 1967, the expressway opened from the Millerstown Exit to the Newport Exit and the newly upgraded section of I-95, at the same time construction began on the section from Thompsontown to the Millerstown Exit.  The following year, the new alignment from south of the Centre County line to Milroy opened.  The same year construction began on the Eisenhower/Hershey Interchange where I-83, I-283, and US 322 all converge and a short section of expressway east to Paxton Street.  Dividing also took place on a section west of State College that year.  In 1969, the expressway opened from Thompsontown to Newport.

The 1970s began with the designation moved from Luthersburg to PA 153 and replaced PA 410.  Also, the Hershey Interchange, then called the Eisenhower Interchange, and the short expressway segment east of it opened.  Construction began on the Mount Nittany Expressway in State College from West Atherton Street to the Penn State University Exit.  The highway was widened from PA 417 to French Creek in Franklin.  In 1971, construction began on four projects to upgrade the highway:  widening and dividing west of Port Matilda to US 220, Mount Nittany Expressway from Lemont to East Atherton Street, new expressway from Dauphin to I-81, and the Commodore Barry Bridge and accompanying expressway from Ninth Street to the approach.  Work began on the Interstate 81 section from the George N. Wade Bridge to the interchange with Interstate 83.  In 1972, expressway construction continued from Mexico to Thompsonville and near Cuba Mills.  Also, work to improve the highway by dividing the lanes of travel began from south of Potters Mills to the Mifflin County line.  The following year, work began on the expressway gap from Cuba Mills to Mexico.  Also in 1973, the dividing project west of Port Matilda concluded.  In 1974, the Commodore Barry Bridge opened to traffic, which signaled the end of the ferry that carried US 322 traffic across the Delaware since 1937.  Also the work to divide the directions of travel from south of Potters Mills to the Mifflin County line concluded.  Also, the bridge over the French Creek in Franklin was replaced with a wider crossing.  In 1975, two new alignments opened:  Cuba Mills to Thompsontown and the connection from Ninth Street to the interchange with Engle Street and Flower Street opened in Chester.  In 1976, the Interstate 81 section of the highway opened to traffic.  In 1979, work began on the missing section of the Mount Nittany Expressway from the Penn State University Exit to Lemont, while at the same time the new expressway section from PA 443 to Interstate 81 opened.  With the opening, the US 322 designation was moved to I-81 and I-83 to bypass Harrisburg.

The first year of the 1980s saw the opening of the first sections of the Mount Nittany Expressway from West Atherton Street to the Penn State University Exit and from Oak Hall to East Atherton Street.  In 1984, construction began from the Penn State University Exit to PA 26, while in the same year, the Hummelstown Bypass was upgraded to expressway standards.  In 1985, the entire Mount Nittany Expressway was completed and opened to traffic.

The 1990s began with the Cornwall Bypass being upgraded to expressway standards in 1991.  In 1997, construction began on the Dauphin Bypass, a segment of expressway from PA 325 to PA 443.  In 1998, construction began on a new expressway alignment from Milroy to Reedsville.  The Dauphin Bypass opened to traffic in 1999 and the latter section opened in 2000.

Work to improve the highway is extending into the 21st Century.  PennDOT is studying the feasibility of an expressway to be built from Exit 123 of Interstate 80, bypassing Phillipsburg, and connecting with the future Interstate 99 west of Port Matilda.  The actual alignment is still being determined, which is proving to be tricky with farmlands and forests forcing engineers to "tip-toe" around them.  On July 18, 2002, PennDOT's transportation study team announced the path of Corridor O.  The proposal goes south of Thompson's Curve and north of Philipsburg and Morrisdale and would be the shortest, least costly and least disruptive of five routes under consideration.  In this plan, only 32 homes would have to be taken instead of 80 or 90 that the other proposals would end up taking.  Also this plan would only cost $400 million, $50 million less than the others.  The price tag does not include bridges and the cost of acquiring right-of-way.  Project website:  http://www.corridor-o.com/.

One of the last remaining gaps of expressway from State College to Harrisburg in the section from State College to Potters Mills.  PennDOT is conducting a needs study to determine where an expressway should be built.  The titled of the study is formally referred to as the South Central Centre County Transportation Study, or SCCCTS for short.  Three alignments are being focused on:  From the eastern end of the Mount Nittany Expressway (past the Tussey Mountain ski area) to the stub-end at Potters Mills, from the southern stub-end of the Bellefonte Bypass (over the Mount Nittany ridge near Centre Hall and Pleasant Gap) to the stub-end at Potters Mills, and a combination of both.  The preferred alternative will be selected by 2002 with construction beginning by 2005.  Project website:  http://www.scccts.org/.

The other gap in the expressway is through the Lewistown Narrows, which is currently the most dangerous stretch of highway in Pennsylvania.  The highway connects two sections of expressway by a two-lane highway.  Construction is projected to begin in the spring of 2002, and be completed in late 2004.  Project websites: http://www.penndot2.com/route22_322/index.html or http://www.eadsgroup.com/narrows/.

Westbound near Watts
Westbound near Watts.
 
Westbound at the PA 35 Exit
Westbound at the PA 35 Exit.
 
Westbound near Thompsontown
Westbound near Thompsontown.  The eastbound lanes are located below
the guide rail on the left side of the picture.
 
Westbound between Thompsontown and PA 35
Westbound between Thompsontown and PA 35.
 
Westbound approaching the PA 35 Exit
Westbound approaching the PA 35 Exit.
 
Westbound near after the PA 35 Exit
Westbound near after the PA 35 Exit.
 
Westbound in "The Narrows," the deadliest part of US 322 between
Westbound in "The Narrows," the deadliest part of US 322 between
Lewistown and Harrisburg.  It will be upgraded to an expressway soon.
 
Westbound in on the Lewistown Bypass
Westbound in on the Lewistown Bypass.
 
Westbound near Yeagertown
Westbound near Yeagertown.
 
Westbound at the PA 655 Exit
Westbound at the PA 655 Exit.
 
Westbound near Milroy
Westbound near Milroy.
 
Westbound nearing the end of the expressway near Milroy
Westbound nearing the end of the expressway near Milroy.
 
Westbound on the Mount Nittany Expressway at the PA 45 Exit
Westbound on the Mount Nittany Expressway at the PA 45 Exit.
 
Westbound on the Mount Nittany Expressway at the PA 26 Exit
Westbound on the Mount Nittany Expressway at the PA 26 Exit.  The
covered-up signs are for the I-99 interchange west of PA 26.
 
Westbound on the Mount Nittany Expressway west of State College
Westbound on the Mount Nittany Expressway west of State College.

Links:
Exit Guide
US 322 Auxiliary Routes
Interstate 81
Interstate 83
Interstate 95
Interstate 99
E-ZPass - Delaware River Port Authority
Commodore Barry Bridge - Delaware River Port Authority
Corridor O - Making Connections
EcoCheck 99-The Environmental Influence of Pennsylvania Interstate 99 - Juniata College
Road to Ruin - US 220/US 322
South Central Centre County Transportation Study
Vision 2020:  Living with I-99
Commodore Barry Bridge - Steve Anderson
Commodore Barry Bridge Photo - Steve Richman
ISTEA - NHS High Priority Corridor 9 - Andy Field
Terminus of US 322 - Dale Sanderson
US 322 Expressway - Steve Anderson
US 322 Junction List - Timothy Reichard
US 322 Meadville - David Brunot
US 322 Pictures - Andy Field/Alex Nitzman
US 22/US 322 Pictures - Andy Field/Alex Nitzman


Information INFORMATION
Western
Entrance:
Ohio state line six miles west of Turnersville.
Eastern
Entrance:
New Jersey state line at the Commodore Barry Bridge in Chester.
Length: 356 miles
National
Highway
System:
PA 58 to I-80 at Exit 70
PA 153 to the New Jersey state line
Names: Twenty-Eighth Division Highway
Mount Nittany Expressway:  Business US 322 to Business US 322
Vietnam Veterans Memorial Highway:  Exit 3 to Exit 4 of I-95
SR
Designations:
SR 0322
SR 0006:  Conneaut Lake to Meadville
SR 0219:  DuBois to Luthersburg
SR 0220:  Port Matilda to State College
SR 0022:  Lewistown to Exit 67A of I-81
SR 0081:  Exit 67A to Exit 70
SR 0083:  Exit 46B to Exit 51A
SR 0202:  West Chester to US 1
SR 0001:  US 202 to Concordville
SR 0095:  Exit 3 to Exit 4
Counties: Crawford, Mercer, Venango, Clarion, Jefferson, Clearfield, Centre, Mifflin, Juniata, Perry, Dauphin, Lebanon, Lancaster, Chester, and Delaware
Expressway: State College Bypass/Mount Nittany Expressway
Reedsville to Lewistown
Concurrent with US 322 from west of Cub Mills to PA 325.
Concurrent with US 322 from Dauphin to I-81.
Concurrent with I-81 from Exit 67A to Exit 70.
Concurrent with I-83 from Exit 46B to Exit 51B.
Hummelstown Bypass
Cornwall Bypass
PA 452 to I-95
Concurrent with I-95 from Exit 3 to Exit 4.
I-95 to the Commodore Barry Bridge
Concurrent
Routes:
PA 58:  Jamestown
PA 18:  Hartstown to Conneaut Lake
US 6:  Conneaut Lake to Meadville
US 19:  US 6 to Meadville
US 62:  Franklin
PA 8:  Franklin
PA 208:  Shippenville
PA 28:  Brookville
PA 36:  Brookville
US 219:  DuBois to Luthersburg
PA 153:  Near Exit 111 of I-80 to Clearfield
PA 53:  Phillipsburg
PA 970:  Wallaceton to Woodland
US 220:  Port Matilda to State College
US 22:  Lewistown to Exit 67A of I-81
I-81:  Exit 67A to Exit 70
I-83:  Exit 46B to Exit 51A
PA 241:  Fontana
PA 72:  Cornwall Bypass
PA 897:  East Earl
Business US 30:  Downingtown
US 202:  West Chester to US 1
US 1:  US 202 to Concordville
I-95:  Exit 3 to Exit 4
Former
Designations:
PA 5  (1925 - 1930):  Meadville to Phillipsburg
PA 5  (1925 - 1933):  Reedsville to Lewisburg
PA 350  (1928 - 1933):  Phillipsburg to Port Matilda
PA 250  (1930 - 1933):  Marthas Furnace to Waddle
PA 250  (1928 - 1933):  Waddle to Potters Mills
PA 53  (1928 - 1933):  Potters Mills to Reedsville
PA 3  (1925 - 1930):  Lewisburg to Hummelstown
PA 250  (1928 - 1932):  Marthas Furnace to Pottersville
US 22  (1926 - 1936):  Harrisburg to Hummelstown
PA 5  (1925 - 1936):  Hummelstown to West Chester
PA 61  (1928 - 1936):  Concordville to Chester
SmarTraveler
Traffic Conditions:
US 1 - New Jersey Turnpike
#211/(215) 567-5678
Area Codes: 814:  Ohio state line to the Perry County line
717:  Juniata County line to the Chester County line
610/484/835:  Lancaster County line to the New Jersey state line

Back to Pennsylvania Highways
Back to Pennsylvania United States Highways
Page updated January 19, 2004.