US 19
William Flinn Highway
Perry Highway


Another highway named after significant members of Pennsylvania history, and not a politician, US 19 was the major corridor in Western Pennsylvania before Interstate 79 was even a thought in President Dwight D. Eisenhower's mind.  The route in 1927 was the same as today with a few exceptions.  In Washington, it followed Maiden Street, College Street, Highland Avenue, Ridge Avenue, and Murtland Avenue.  It went from Canonsburg through Bridgeville to Carnegie.  The designation followed Noblestown Road, Mansfield Avenue, South Main Street, West Carson Street, Point Bridge, Manchester Bridge, West Ohio Street, East Ohio Street, and Butler Road in Pittsburgh before heading to Butler on the current PA 8 alignment.  From Butler it traveled to Slippery Rock, Franklin, Meadville, Waterford, and onto Erie.  In Meadville, the designation followed Mercer Street, Water Street, Poplar Street, Park Avenue, and Baldwin Street.  In Erie, it followed Peach Street into downtown.  In 1929, the designation was moved to Federal Street and Perrysville Avenue in Pittsburgh because the designation was switched to the current alignment.  The designation changed course at Cambridge Springs to McKean and onto Erie on the current PA 99 alignment.  The highway was unimproved from Middle Lancaster to Portersville, Rose Point to Leesburg, Mercer to Hadley, and Sheakleyville to West Union.  From Leesburg to Mercer, US 19 was still under construction.

In 1931, the highway was finished with the exception of a section from Custards to Meadville which was still under construction.  Also that year, the designation was moved to Ridge Avenue, Chateau Street, and Marshall Avenue in Pittsburgh.  In Erie County, US 19 was placed on the current alignment from Meadville to Waterford and placed on the current PA 97 alignment to Erie.  In 1934, construction on the highway was complete and so was the West End Bridge.  With the opening, came another change in the route to Ridge Avenue, Manchester Avenue, Allegheny Avenue, and California Avenue.  In 1937, the designation was moved to the current alignment from Waterford to Erie.  In 1939, highway was widened from Pittsburgh to Wexford.

The 1940s saw the start of the bulk of widening work along US 19.  In 1940, it was widened from Laboratory to Washington, Washington to north of town, Canonsburg, Portersville to the Lawrence County line, US 6/322 to one mile south of Kerrtown, and from Kerrtown to Meadville.  In 1941, the designation was changed with PA 519 to bypass Canonsburg on the current alignment to Pittsburgh on Banksville Road, Woodville Street, and Wabash Avenue.  Widening took place east of Morganza to Pittsburgh.  In 1945, the designation was moved to Chateau Street between the West End Bridge and Marshall Avenue.  In 1948, the highway was widened north of Washington to PA 519 and the designation moved to Cochran Road and Beverly Road from McFarland Road in Dormont.  In 1949, the highway was widened from Canonsburg to Morganza.

The 1950s continued to see widening work taking place along the highway.  In 1951, widening work took place on the route from Kearsage to Erie.  Construction began on the long-awaited Penn-Lincoln Parkway began in Pittsburgh, which ended up using a small section of the US 19 alignment near Saw Mill Run Boulevard.  The following year, work was performed from Wexford to Ogle.  Also in 1952, the West End Bypass opened to traffic from the Penn-Lincoln Parkway to PA 837.  In 1953, the designation was changed in Washington. Northbound traffic was moved to Lincoln Street, while southbound traffic was shifted to Highland Avenue, College Street, and Maiden Street.  The following year, widening continued from Ogle to Harmony, and north of Harmony.  In Meadville, the designation was changed to Park Avenue and in Pittsburgh, the Penn-Lincoln Parkway opened to traffic.  In 1955, the highway was widened at the Greene/Washington County line, a section south of Laboratory, and south of Portersville.  The next year, the section from Waynesburg to Morrisville saw widening work performed.  In 1958, construction to widen and divide the highway took place north of Washington to Morganza, Banksville Road, Dormont to the Parkway, Wexford to Zelienople, at the intersection of US 422, Kerrtown to Meadville, and in Cambridge Springs.  In 1959, widening was completed south of Portersville.

The 1960s saw construction on the Interstate System swing into full gear which even affected US 19.  While not currently signed on a long section of Interstate highway, in the 1960s, it was signed on parts of I-79 and I-70.  I-70 was under construction around Washington, which opened to traffic the following year.  In 1961, construction began on the section of I-79 from US 40 to I-70 and opened in 1962.  In 1963, the remaining sections of the Interstates opened around Washington and with that, the US 19 designation was moved onto I-79 and I-70.  Also that year, the West End Bypass opened to traffic, with southbound traffic utilizing Steuben Street.  In 1967, the US 19 designation was moved back into Washington on Maiden Street, Lincoln Street (northbound), College Street (southbound), Highland Avenue, Ridge Avenue, and Murtland Avenue.

The 1970s began with a construction project that was caused by the Interstate system.  In 1970, construction to widen and divide the highway from Erie to Kearsage started and was competed in 1971.  That same year, construction started on a new alignment from Meadville to north of town and on the section of Ohio River Boulevard from Pennsylvania Avenue to near the California Avenue/Marshall Avenue intersection.  In 1973, Ohio River Boulevard opened to traffic.  In 1974, the new alignment from Meadville to north of town opened and the US 19 designation was moved onto the new highway.

With traffic increasing on the North Shore, construction on the $8 million project to connect the two sections of Ohio River Boulevard together began in Spring 1987 from Allegheny Avenue to Western Avenue.  Phase Two of the project would begin in January 1988, which would consist of a new interchange between the expressway and the West End Bridge.  The bridge would be closed for two years while it underwent rehabilitation and new ramps were built at the northern end for the interchange.

On January 14, 1992, the project finished 40 years after first being planned and opened to traffic for that day's afternoon rush hour.  With the new expressway opened, the temporary interchange at Ridge Avenue was eliminated.  Dick Enterprises, now Dick Corporation, the contractor for the project, finished the $45 million West End project which included rehabilitation of the West End Circle and Bridge 10 months ahead of schedule.  The bridge reopened three months earlier than the projected 16 months in July 1991.

PennDOT is studying the problems of the West End Circle, which causes congestion as US 19, PA 51, and PA 837 intersect.  The improvement project consisting of creating a regular intersection at the end of the West End Bridge would begin after the completion of the Fort Pitt Bridge and Tunnel rehabilitation project.  Once the project was finished, Saw Mill Run Boulevard traffic would travel over South Main Street and no longer have to travel around the circle to get to and from the bridge.  Project website:  http://www.westendimprovements.com/.

Links:
US 19 Auxiliary Routes
Ohio River Boulevard
West End Improvements
JCT US 6, 19, 322 - David Brunot
Terminus of US 19 - Dale Sanderson
US 19 Junction List - Timothy Reichard
West End Bridge - Bruce Cridlebaugh
William Flinn Highway - Adam Prince/Bruce Cridlebaugh


Information INFORMATION
Southern
Entrance:
West Virginia state line 1/2 mile south of Mount Morris.
Northern
Terminus:
US 20 in Erie.
Length: 187 miles
National
Highway
System:
Washington to Pittsburgh
Names: William Flinn Highway:  West Virginia state line to Pittsburgh
Perry Highway:  Pittsburgh to Erie
SR
Designations:
SR 0019
SR 0279:  Exit 5A to Exit 5C
SR 0006:  US 322 to US 6N
Counties: Green, Washington, Allegheny, Butler, Lawrence, Mercer, Crawford, and Erie
Expressway: Concurrent with I-279/US 22/US 30 from Exit 5A to Exit 5C.
Concurrent with PA 51 from I-279/US 22/US 30 to PA 837.
West End Bridge to Marshall Avenue in Pittsburgh
Concurrent
Routes:
PA 21:  Morrisville to Waynesburg
US 40:  Laboratory to Washington
US 22:  Exit 5A to Exit 5C of I-279
US 30:  Exit 5A to Exit 5C of I-279
I-279:  Exit 5A to Exit 5C
PA 51:  I-279 to PA 837
PA 65:  West End Bridge to Marshall Avenue
PA 68:  Zelienople
PA 488:  Portersville
PA 208:  Leesburg
US 62:  Mercer
PA 58:  Mercer
PA 258:  Mercer
US 6:  US 322 to US 6N
US 322:  US 6 to Meadville
PA 198:  Saegertown
PA 97:  Waterford to three miles north of town
Former
Designations:
PA 8  (1911 - 1926):  West Virginia to Meadville
PA 5  (1911 - 1926):  Meadville to Erie
Yellow Belt
Pittsburgh Belt System:
Connor Road to PA 121
Washington's Trail
Washington's
Trail:
PA 65 south to PA 65 north
PA 910 to PA 528
Mercer Road to Portersville
Meadville to Fort LeBoeuf
PennDOT
Traffic Cameras:
West End Bridge (Southhbound)
West End Bridge (Northhbound)
Area Codes: 724/878:  West Virginia state line to the Allegheny County line; Wexford to the Crawford County line
412/878:  Washington County line to Wexford
814:  Mercer County line to Erie

Back to Pennsylvania Highways
Back to Pennsylvania United States Highways
Page updated March 12, 2004.
Content and graphics, unless otherwise noted, copyright © Jeffrey J. Kitsko. All rights reserved.
Information sign and US shield courtesy of Richard C. Moeur.
Pittsburgh Belt System and Washington's Trail shield courtesy of Bruce Cridlebaugh.
Information courtesy of the Pennsylvania Department of Transportation, Rand McNally, AAA, General Drafting, and Bruce Cridlebaugh.