PA 576 PA Turnpike 576
Southern Beltway


This is a highway that is still in the design phase of the construction process.  It will be a toll road from the future Mon-Fayette Expressway to I-79 near Canonsburg to the Southern Expressway - PA 60. Already, many people in Findlay Township are coming out against construction.  The reason: the proposed route would cut through many neighborhoods and divide families.  For more information about the Southern Beltway, check out the Pennsylvania Turnpike's Expansion Projects Page.

In compliance with the 1991 US Intermodal Surface Transportation Efficiency Act, a Congestion Management System (CMS) Analysis and a Major Investment Study (MIS) were conducted for the entire Southern Beltway corridor.  Along with the Pennsylvania Turnpike Commission, the Southwestern Pennsylvania Regional Planning Commission (SPRPC) was the lead agency that pushed for the two studies.  The integrated report recommended the construction of a tolled expressway to alleviate deficiencies.  The report initiated the Environmental Impact Study phase of construction.  The SPRPC passed a resolution on September 26, 1996 endorsing the CMS/MIS report.

The Turnpike Commission has been given approval by the Federal Highway Administration for final design on May 11, 1998.  PA 60 at the Pittsburgh International Airport to US 22 is the section that has been given this approval.  The final environmental impact study will be completed in three years and will pinpoint the exact location of the expressway.

Construction of the highway also includes widening US 30 at the interchange, reclaimed strip mines, and landfills, and will displace seven families and a greenhouse.  There is another problem that is facing the Turnpike Commission:  environmental impact.

One problem is that short-eared owls, which are on the Pennsylvania Game Commission's endangered species list, nest near the proposed Bald Knob/Ridge Road interchange.  Turnpike engineers will monitor the presence of the owls during construction.  About 87 acres of nesting land will be impacted by construction, so the PTC will set aside other lands for the birds to nest. Other environmental problems will be with minimizing impact to streams and replacing eight acres of wetlands.

The project costs will amount to $150 million which include final design, right-of-way acquisition, utility relocation, waste disposal, and construction.

The plans for the US 22 to I-79 project were presented at a public meeting in 1997.  Three alignments were chosen that parallel the Allegheny/Washington county line. One passes to the north and east of McDonald Borough while the two others bypass McDonald to the west and south.

Two other sections are under evaluation currently.  From US 22 to I-79 and from I-79 to the Mon-Fayette Expressway.  Six million dollars have been appropriated for preliminary engineering and environmental clearance and $15 million for final design of the PA 60 to US 22 section.  In addition to that, $20 million has been committed for preliminary engineering for two other projects along the corridor ($10 million each).  Records of decision are expected to be completed in the First Quarter 2002 for the US 22 to I-79 section and in the First Quarter 2003 for the I-79 to Mon-Fayette Expressway section.

This highway has recently classified by congress as a High Priority Corridor.  When completed, this highway will be located 15 miles outside of Pittsburgh's Golden Triangle.  It will also help in connecting the Mon River valley to Pittsburgh International Airport.

Obviously, the critics of the highway so far have been the residents along the proposed alignment; however, one unlikely opponent has come forward in 2000.  State representative John Maher, from Upper St. Clair in Allegheny County has noted the lack of interchanges with important highways, commenting that, "The absence of access for people along this highway is so complete that it's no surprise that people are rethinking support of this road."  Critics say the toll road does not include interchanges with busy highways such as US 19 and PA 50.  Louis Philips, the head of the Route 50 Corridor Commission, said that Turnpike officials will not allocate the necessary $35 million for the interchange.  He has also mentioned that he will not support the highway if money is not made available for the connection.  PTC officials have said that an access road is a local project and should be handled by other state and regional agencies.  Representative Maher said he objected to the toll road for the same reason as Louis Philips.  He also opposes a plan for the beltway to travel over Canonsburg Lake, saying, "Any route that would disturb Canonsburg Lake would be wholly unacceptable."

There has been speculation as to what designation will be placed on this highway when it is completed.  I had believed that it would receive an odd PA Turnpike x43 since it will be a spur off of PA Turnpike 43/Mon-Fayette Expressway.  Matt Boyko, contributor to Pennsylvania Highways and Pittsburgh Highways, forwarded me an e-mail response from Joe Agnello of the Pennsylvania Turnpike Commission.  The message said, "Based on our current plans, the Southern Beltway will be designated Pa. Route 576 or Pennsylvania Turnpike 576. Ultimately, we believe that major chunks, at the least, of both the Mon/Fayette Expressway and Southern Beltway systems will receive Interstate designation from the Federal Highway Administration."

Completion Information

Segment

Status

Link to:


TO

Final Design
(Step 10 of 10 Step
Transportation Project Development Process)

http://www.faeco.telerama.com/pa-60to.htm


TO

Development and Review of Detailed Alternatives
(Step 5 of 10 Step Transportation Project Development Process)

http://www.faeco.telerama.com/us-22to.htm


TO

Development and Review of Preliminary Alternatives
(Step 4 of 10 Step Transportation Project Development Process)

http://www.faeco.telerama.com/i-79to.htm

Links:
Exit Guide
Pennsylvania Turnpike Commission
Pennsylvania Turnpike Commission Expansion Projects-Southern Beltway
Fayette Expressway Completion Organization:  Southern Beltway Corridor
1999 Road to Ruin:  Mon/Fayette & Southern Beltway, PA
Cecil Toll Road: Just Say No
ISTEA/NHS/TEA-21 High Priority Corridor 31 - Andy Field


INFORMATION
Western
Terminus:
JCT PA 60 at the Pittsburgh International Airport.
Eastern
Terminus:
JCT PA Turnpike 43 near New Eagle.
Length: 31 miles upon completion
National
Highway
System:
Entire length
Name: Southern Beltway
SR
Designation:
SR 0576
Counties: Allegheny and Washington
Concurrent
Routes:
None
Former
Designations:
None
Speed Limit:
Emergency:
Highway
Conditions:
Area Codes: 412/878:  Allegheny County
724/878:  Washington County

Back to Pennsylvania Highways
Back to Pennsylvania Toll Highways
Page updated October 26, 2001.
Information sign courtesy of Richard C. Moeur.
Pennsylvania shields courtesy of James Lin.
Planning information courtesy of Joe Agnello of the Pennsylvania Turnpike Commission, the "Turnpike Traveler," the Fayette Expressway Completion Organization, Greensburg Tribune-Review, and Matt Boyko.