Bud Shuster Highway
Appalachian Thruway
The first section to be built of this Interstate that gives some indigestion was the section from south of Bedford Springs to Exit 3 in 1969. This was being built in conjunction with the US 30 bypass of Bedford. The section from south of Bedford Springs to the interchange with Business US 30 is a two-lane limited-access design, known as a "Super-2." The following year, this section opened to traffic. While that was taking place in 1970, the section that was the Tyrone bypass was started, which is the section from Exit 45 to Exit 52.
In 1974, while construction continued on the Tyrone bypass, construction began on a section from Exit 3 to the Bedford/Blair County line. In 1976, the Tyrone bypass opened to traffic.
In 1980, the section from Exit 3 to the Bedford/Blair County line opened to traffic. In 1982, construction began on the section from Newry to Exit 31. This was done in conjunction with the construction of the US 22 expressway to Ebensburg. In 1984, construction began on the section from Exit 31 to the Exit 33. In 1986, this section opened to traffic as the "missing-link" from the Bedford/Blair county line to Newry hit the maps as proposed. In 1987, construction began on this section. In 1988, the section from Newry to East Freedom opened and remaining section opened to traffic in 1989.
In 1991, construction began on the "missing-link" on the US 220 expressway, which comprised the Interstate from Exit 33 to Exit 45. In 1994, this section opened which allowed traffic an uninterrupted flow from south of Bedford Springs to north of Tyrone: free of cross traffic, traffic signals, and slow trucks trying to navigate narrow, mountainous, old US 220.
However, things were not all quiet on the Central Front. In 1996, Representative Bud Shuster who was responsible for funds for the upgrading of US 220, had this highway designated an Interstate. Something that I agreed should have happened; that is where the agreeing stops! Bud had his highway designated I-99 and had the designation written into law. It was bad enough that he had the highway end near his cousin's car dealership, and violate Interstate highway numbering system too! It should have been numbered I-576, 776, or 976. I like the last...a fitting number for a dirty politician. The Washington Post has reported that he has been under investigation for illegal highway funding acts, and was reprimanded by the House ethics committee for accepting improper gifts and favoring a lobbyist by the name of Ann M. Eppard. In September 2000, the Committee on Standards of Official Conduct criticized Shuster for "serious official misconduct" but did not penalize him any further.
On January 4, 2001 Bud Shuster announced he was retiring after 14-terms in the House of Representatives due to recent "health scares." He said he didn't want to wait until the end of his term because he didn't want to become a lame duck. But its OK do damage the numbering system and name a highway after himself. We thought maybe we had finally gotten rid of the name Shuster in congress; however, we were wrong. In March 2001, his son Bill announced he would run for his father's vacant seat. He won the May 15 election by 52% over his opponent Scott Conklin (D).
After almost four years of construction, the next section to open was from the Mount Nittany Expressway to the Bellefonte Bypass on November 25, 2002. Ribbon cutting ceremonies started at 10 AM at the Park Avenue interchange near Beaver Stadium, and the highway opened officially.

Piece of ceremonial ribbon used at the opening of
the
section from US 322 to PA 26.
(Geoff Hatchard and PENNDOT)
The official name of the project was the PA 26 Relocation Project, which started in January 1999 and cost $195 million to build. The Bellefonte Bypass section of the expressway was built in 1971 and opened in 1972 as a "Super-2" expressway, a two-lane expressway built on a four-lane right-of-way. In 1997, the other lanes were built to make it a four-lane highway. As other expressway projects in Pennsylvania, an open house was held on October 26, 2002 called a "Roll & Stroll." Around 1,000 people are estimated to have walked, biked, skated and strolled along the new expressway. A four-mile race to benefit the United Way of Centre County was held on the right-of-way, with Penn State's ROTC cadets participating with the public. This section will not officially become part of I-99 until 2007 when the Bald Eagle to Mount Nittany Expressway sections are completed.
|
|
|
|
I have been on this Interstate and it is confusing to have two markers designating this expressway. However, there are no shields on any overhead signs along the roadway. The only signs I have seen that have I-99 shields on them are the Exit 146 signs on the Turnpike and from US 22. The only way that anybody could tell their on I-99 are the many TO I-99 signs along its path. Could PENNDOT be showing their disapproval of this Interstate?
PENNDOT has announced its plans for I-99, which are listed below:
| County | Area of Study | Type of Project | Cost |
| Centre | I-80/I-99 Bellefonte Interchange | Engineering | $5,500,000 |
| Right-of-Way Construction |
$61,000,000 | ||
| North and South of Port Matilda | Right-of-Way Construction |
$135,100,000 | |
| Centre/ Blair |
Bald Eagle to Port Matilda | Right-of-Way Construction |
$166,960,000 |
Links:
Exit Guide
Interstate 99 Pictures
I-99/US 220 Construction Progress Map
I-99/US 15 Construction Progress Map
US 220
Corridor O - Making Connections
- PENNDOT
EcoCheck 99-The
Environmental Influence of Pennsylvania Interstate 99 - Juniata College
North Altoona Access Study
- PENNDOT
Road to Ruin - US 220/US
322 - Friends of the Earth
Susquehanna Beltway
- PENNDOT
Vision 2020: Living with I-99
Future Interstate
99-North of I-80 - Brian Polidoro
Interstate 99 - Andy Field/Alex Nitzman
Interstate 99 - David Steinberg
Interstate
99 in Centre County - Geoff Hatchard
Interstate 99
Pictures - Andy Field/Alex Nitzman
I-99/US
220 Construction Pictures - Tim Reichard
ISTEA - NHS High Priority Corridor 9 - Andy Field
Kurumi's Trippy Drive '71 - Scott Oglesby
|
UNDER CONSTRUCTION
INTERCHANGE
WITH I-80
NORTH OF
I-80 |
INFORMATION |
|
| Southern Terminus: |
Business US 220 in Bedford. |
| Northern Terminus: |
PA 350 in Tyrone. |
| Length: | 59 miles |
| National Highway System: |
Entire length |
| Names: |
Appalachian Thruway Bud Shuster Highway: Exit 1 to Exit 52 |
| SR Designation: |
SR 0099 |
| Counties: | Bedford and Blair |
| Multiplexed Route: |
US 220: Entire length |
| Former Designation: |
US 220 (1970 - 1996) |
| Speed Limits: | See exit guide |
| Emergency: | 911 |
Highway Conditions: |
Interstate 99 Conditions |
| Area Code: | 814 |