A major Problem in the life of the Naval Reservation has been
the need of an adequate water supply. In the early days, water
was supplied by contract with local railroads. The water was transported
in tank cars from the Guantanamo City aqueduct to the docks at
Caimanera or Deseo, and later Boqueron, and thence to the station
in Navy barges. The barges generally docked at the station wharf
of South Toro Cay and the water was discharged to pipes running
up to the 100,000 gallon reservoir on North Toro Cay, as related
in a previous chapter. One barge habitually docked at a pier on
the east side of North Toro, the pier being located south east
of Commandant's Hill. From there a shorter pipeline ran to the
same reservoir. However, the South Toro station wharf was the
point at which water was drained off from the reservoir into smaller
water barges for delivery to population centers on the Reservation.
Later on, in 1913, a 200,000 gallon tank (No. 38) was constructed
on the hill south of the new "Main Station", and this
tank became the principal water storage. The tank on North Toro,
however, was utilized for many years thereafter.
The foregoing method of transportation made the cost of the water
preposterously high and was a vital factor in retarding the development
of the station as a major base for the Fleet. Other sources were urgently
needed. In 1908 a water distillation plant was erected on Hospital
Cay. The equipment had been removed from Dry Tortugas and although
it had a rated capacity of 2000 gallons per hour, it was never
really operative, as the equipment was so nearly worn out that
it failed to produce acceptable water.
In the early days numerous borings were made in an effort to obtain
potable water by shallow wells. Earliest borings were on Hospital
and Toro Cays (1905-07), without success. Rainfall in the immediate
area of the Reservation is infrequent, therefore no water supply
could be expected from small catchment areas, as can be done at
other tropical locations. The Stewart Engineering Company in 1917
tried to obtain potable water from wells, operating under contract.
Instead they found copper. A couple of mine shafts were dug on
a hill, now called Copper Mine Hill, Just to the westward of the
Anti-Aircraft Training Center, and the company requested authority
to operate their diggings as a copper mine. Authority was denied,
presumably because of restrictions on private enterprise imposed
by the lease agreement. Also the quality of the-copper ore was
perhaps not high enough to warrant exploitation.
During Fleet concentrations in this area, water barges had to
be operated day and night in order to ferry water from Cuban sources
to meet Fleet requirements. Peak deliveries during Fleet concentrations
varied between 5,000,000 and 8,000,000 gallons per month.
"Hydrographic Office Chart No. 5198 (September 1928) indicates
& water tank located north of the station boundary near the northern-most
reaches of Granadillo Bay (south of Boqueron). The Cuba Eastern
Railroad (now the Guantanamo and Western) had spur tracks running
to this tank. A pipeline led from the tank to a wharf located
at the station boundary on Granadillo Bay. Presumably the station
received water under contract at this wharf.
During 1929 and 1930 an effort was made to construct an impounding
area behind the concrete butts of the rifle range, to catch run-off
from the hills. An outlet works was constructed but the entire
project was abandoned when, after a heavy rainfall, the porous
soil permitted the water to seep under the concrete butts. The
remnants of this project are in evidence adjacent to the Public
Works Nursery and not far from the 17th hole of the present-day
golf course.
About 1931-32 the water contract was transferred from the Guantanamo
Railroad Company, on the Caimanera side, to the Guantanamo and
Western Railroad Company. It appears that for some time water
was being obtained from both the Caimanera and Boqueron sides,
but this contract indicates a definite shift to Boqueron at this
time. The Guantanamo and Western had better facilities to transfer
the water to the barges. The Navy also received a better price
scale in the change of contract. The new prices ranged downward
from $3.12 per 1000 gallons, compared with the former minimum
price of $3.25 per 1000 gallons.
The present phase of the water supply problem began in 1939, when
action was initiated to enter into a long term contract for the
purchase of water, as provided for in a congressional act of 1934.
After competitive bidding, an award was made to Henri Schueg Chassin
Company of Santiago de Cuba on 25 July 1938. The contract became
effective on 1 July 1939, when water was first delivered. The
contract runs for 20 years, with renewal options each 10 years.
It required the contractor to construct a water intake and pumping
plant at the Yateras River, about 11 miles northeast of the main
part of the Reservation, a surge tank about halfway between the
Reservation and the pumping plant, a water treatment plant on
the Station and a pipeline connecting the pumping plant with the
surge tank and the treatment plant. The treatment plant will become
the property of the Navy at the expiration of the contract.
The acquisition of water by this means was the beginning of a
phenomenal expansion of Base facilities. In 1941-42 it became
necessary for the Navy to construct additional pumping facilities
three times larger than the original plant. The Navy constructed
an additional surge tank and a larger pipeline parallel to the
original line. The Navy also constructed additional treatment
plants on the Base during this period. The Henry Shueg Chassin
Company by agreement was privileged to buy from the Navy the additional
facilities constructed during the war years, located outside of
the Base. This option was exercised on 3 December 1947 and all
off-Base facilities are now owned by the water contractor. Chronologically,
however, this part of the account is getting ahead of the remainder
of the history.
Go to Chapter Eleven