Items in red are completed.
|
Project Start |
November 29, 1999 |
|
Shift Traffic to Southbound Bridge |
December 4, 1999 |
Pile Driving Begins ( Four test piles) |
December 21, 1999 |
| Test Piles Completed (Lengths 31-48 ft) | January 6, 2000 |
| Demolition of Span 11 Existing Bridge Begins | January 10, 2000 |
|
Finish Building Northbound Bridge and Roadway |
September 2000 |
|
Shift Traffic to Northbound Bridge |
September 2000 |
|
Demolition of old southbound bridge span 1 |
October 2000 |
| Pile Driving Begins | October 2000 |
| Complete Demolition of southbound Bridge | February 2000 |
| Completion of Concrete Bridge Deck | April 2001 |
| Completion of Earthwork and Paving | May 2001 |
| Final Clean UP Sod and Punch List | May 2001 |
| Project Completion | October 2001 |