Tomoka River Bridge
Construction Schedule

Items in red are completed.

Project Start

November 29, 1999

Shift Traffic to Southbound Bridge

December 4, 1999

Pile  Driving Begins ( Four test piles)

December 21, 1999
Test Piles Completed (Lengths 31-48 ft)  January 6, 2000
Demolition of Span 11 Existing  Bridge Begins January 10, 2000

Finish Building Northbound Bridge and Roadway

September 2000

Shift Traffic to Northbound Bridge

September 2000

Demolition of old southbound bridge span 1

October 2000
Pile Driving Begins October 2000
Complete  Demolition of southbound Bridge February 2000
Completion of Concrete Bridge Deck April 2001
Completion of Earthwork and Paving May 2001
Final Clean UP Sod and Punch List May 2001
Project Completion October 2001
 