CONSTRUCTION NEWSLETTER
Click on photo for a larger view
In the photo above, the concrete barrier wall is being poured by a process called slip forming. The concrete is delivered to the project and is poured into the front of the slip form machine. The concrete falls into a metal form where a series of vibrators compact it. As the machine moves along the finished wall slips from the rear of the form. If conditions are correct, and the concrete is not too wet, the wall stays standing without support. As the finished wall slips from the rear of the form, the workers repair any blemishes in the concrete.
We anticipate switching traffic onto the new bridge around the first week of October. A temporary concrete barrier wall will be placed in the center of the bridge and roadway to separate northbound and southbound traffic. These will be removed after the new southbound bridge is complete and the traffic is returned to the normal location. Since the new bridge will have sidewalks, it should be much safer than the existing narrow bridge for pedestrian and bike traffic.
Additional information will follow as the construction progresses. Should you have any questions, please contact me at (904)677-8740.
Sincerely,
Thomas R. White, PE
Senior Project Engineer
OUR WEB ADDRESS HAS CHANGED FOR MORE INFO AND PICTURES, VISIT OUR WEBSITE @ www.bridgepros.com/tomoka