CONSTRUCTION NEWSLETTER

    Vol. I. No 8

   Beams 1 Span 1 R.jpg (47944 bytes)

    Click on photo for a larger view

In the photo above, the bridge beams have been placed across the final span linking the bridge from shore to shore. The forms will be placed next, and the last section of bridge floor will be poured. Following that, other bridge related activities will include placing the barrier walls on the bridge, grooving the bridge floor to prevent hydroplaning and application of a coating on the exposed concrete to protect it and provide a uniform color and texture.

The project is on schedule, with 47% of the contract time used. The drainage subcontractor has completed drainage on the north side of the bridge and will begin laying pipes and installing drainage structures on the south side of the bridge soon. Roadway construction is underway, and the change in elevation from the old bridge to the new bridge is now visible. When roadway construction on the north side is complete, the subcontractor will switch to the south side of the bridge and begin to raise that side to grade.

Part of our job as construction manager is to test all the materials used in the bridge. This involves sampling and testing the concrete both as it is delivered and after it hardens. So far all the concrete tested on the project meets the specification, and none has been removed. Testing is also performed on the reinforcing steel, the soil the roadway is placed upon and the asphalt used in the road. The rock shown under the bridge in the photo above, is tested to insure it will protect the shore from future erosion during storms.

Additional information will follow as the construction progresses. Should you have any questions, please contact me at (904)677-8740.

Sincerely,

 

 

Thomas R. White, PE

Senior Project Engineer

 