CONSTRUCTION NEWSLETTER

June 20, 2000

    Vol. I. No 7

   aerial_tomoka_5.jpg (53054 bytes)

    Click on photo for a larger view

In the photo above, the bridge construction approaches the south shore. The photo was taken from Ranger Construction’s helicopter. Ranger Construction is a subcontractor performing the roadway and drainage construction on the project.

The project is on schedule, with 40% of the contract time used. The drainage subcontractor has started laying pipes and installing drainage structures. After completion of the drainage, the next phase will include roadway construction starting on the north side then working on the south side.

The bridge construction is moving along with all the pilings on the northbound bridge complete. The beams which support the bridge floor are in place with the exception of the last span. The form work is progressing in preparation to pour the next three sections of bridge floor. This should occur in about three weeks.

Additional information will follow as the construction progresses. Should you have any questions, please contact me at (904)677-8740.

Sincerely,

 

 

Thomas R. White, PE

Senior Project Engineer

 