RS&H CS


February 29, 2000

TO: Highway US-1 Neighbors

RE: CONSTRUCTION NEWSLETTER

vol. I. No 5

SR-5 US-1 Low level bridge replacement over the Tomoka River.

In the photo above, the concrete beams have been set and the forms which will support the floor (deck) of the bridge are partially complete. Temporary wood forms support the wet concrete until it hardens. After the concrete has hardened, the wood forms will be removed and re-used on the next section of the bridge.

The project is on schedule, with 28% of the contract time used. The bridge structure takes much longer to complete than the earthwork, drainage and paving work for the new roadway. The roadway construction work will commence soon and be coordinated to finish when the new northbound bridge is complete.

The schedule shows opening the new bridge late in September of 2000. This date may change depending on weather conditions, which delay the work.

Our company is managing another construction project for the DOT in Ormond Beach. The project involves resurfacing A1A from SR-40 north to Roberta Road. If you travel this area, see our website for that project for traffic and other information at www.bridgepros.com/a1a

Additional information will follow as the construction progresses. Should you have any questions, please contact me at (904)677-8740.

Sincerely,

 

Thomas R. White, PE

Senior Project Engineer