February 29, 2000
TO: Highway US-1 Neighbors
RE: CONSTRUCTION NEWSLETTER
vol. I. No 4
SR-5 US-1 Low level bridge replacement
over the Tomoka River.
FIN: 240845-15201 WPI: 5119225
State Proj. No. 79030-3502 Contract No.: 20,687
F.A.P. No.: 4857 025 P Progress: 89 days used
of 499 days
`In the photo above, concrete is being placed
into the form for pier 7. When the forms are removed, this part of the structure
will support the beams which support the floor of the bridge. This month we will
answer some frequently asked questions about the project:
- Q: Why is the bridge under construction
during bike week.
- A: Since the project will take 499 days to
complete, it would be impossible to schedule construction and not interfere
with any area special events. The DOT is aware construction projects impact
both the traveling public and local businesses. In order to minimize the
impact, they have provided an incentive on this project for the contractor
to complete their work early. A bonus in the amount of $2,500.00 will be
paid to the contractor for each day the project is completed prior to the
499 contract work days. ie: (finish one month early and get a bonus
of $75,000.00)
- Q: Why were the large concrete piles
sticking up in the air?
- A: The first piles installed (test piles)
are made longer than the others in case the shallow layers of soil are
unable to support the weight of the bridge. Once these first test piles are
driven, then the rest of the piles are constructed at a length which matches
the soil conditions.
- Q: Why do the detours extend so far away
from the bridge?
- A: By making the spans longer, there will be
fewer rows of pilings in the river for the new bridge. In order to make the
spans longer, the beams need to be larger. The clearance below the bridge
could not be reduced, so the roadway will need to be raised approximately
three feet. In order to make a smooth transition onto the bridge, and to
install new drainage pipes, the roadway will be reconstructed for several
hundred feet on each side of the bridge.
Additional information will follow as the
construction progresses. Should you have any questions, please contact me at
(904)677-8740.
Sincerely,
Thomas R. White, PE
Senior Project Engineer