The following is an overview of the upcoming tentative construction activities.
Construction of the north end of Bridge: The piles which support the north abutment have been installed and will be cut to length soon. Earthwork to reshape the river bank and forms to construct the concrete abutment will now commence.
Demolition of the first section of the old bridge: The first span of the old northbound bridge has been removed, and the next span will be removed soon. Since the new bridge will have longer spans than the old bridge, fewer rows of piling will be in the river, making boating below the bridge easier.
Concrete Sheet pile retaining wall: Since the surface of the new bridge will be higher by about three feet, the roadway approaches will need to be raised as well. A wall will be constructed along the Tomoka Yacht Club to support the additional fill.
Clearance under new bridge: Since the spans of the new bridge will be longer, reducing the number of piling which obstruct the channel, the beams which support the floor of the bridge will be larger. The existing clearance from the bridge to the river will remain the same and the roadway will be raised.
Additional information will follow as the construction progresses. Should you have any questions, please contact me at (904)677-8740.