CONSTRUCTION NEWSLETTER
Click on photo for a larger view
SR-5 US-1 Low level bridge replacement over the Tomoka River.FIN: 240845-15201 WPI 5119225 State Proj. No. 79030-3502 Contract No.: 20,687 F.A.P. No.: 4857 025 P Progress: 452 days used of 528 days
During fill placement for the widening on the north side of the bridge, a soil failure, shown in the photo above, occurred. The DOT Geotechnical engineers visited the project, and soil boring was performed. The soil samples revealed a layer of muck deep below the roadway surface. The muck is unable to support the weight of the additional fill placed to widen the roadway causing the settlement shown in the photo above. Since the muck is deep under the roadway, it cannot be removed. A wall of steel piling will be placed along the edge of the road which will contain the muck and allow it to support the road. After installation, the steel wall will not be visible since it will be driven into the soil. The addition of the wall will delay the opening of the southbound roadway.
Progress is continuing on the bridge. The concrete floor is now in place. Next the concrete walls will be placed, and then the guardrails will be installed. Sod has been placed on the south end of the project, and all the drainage and underground work is complete. Roadway construction is continuing on the north end of the project.
Additional information will follow as the construction progresses. Should you have any questions, please contact me at (904)677-8740.
Sincerely,
Thomas R. White, PE
Senior Project Engineer
OUR WEB ADDRESS HAS CHANGED AND INCLUDES OTHER PROJECTS UNDERWAY. VISIT OUR WEBSITE @ www.rsandhcsprojects.com