CONSTRUCTION NEWSLETTER
Click on photo for a larger view
February 22, 2001
In the photo above, the old bridge has been completely removed and stockpiled while it is being broken into pieces small enough to be transported to the recycling crusher.
As of today, the last sections of concrete piling which will support the bridge are being installed on the north side of the bridge. The concrete beams which support the bridge have been installed on six of the seven spans, two spans have had the concrete deck poured, and the forms for the next four spans are being constructed.
Although the schedule shows the contractor behind, the crew which has been performing demolition work will now assist the crew constructing the new bridge and production should increase.
Additional information will follow as the construction progresses. Should you have any questions, please contact me at (904)677-8740.
Sincerely,
Thomas R. White, PE
Senior Project Engineer
OUR WEB ADDRESS HAS CHANGED FOR MORE INFO AND PICTURES, VISIT OUR WEBSITE @ www.bridgepros.com/tomoka