CONSTRUCTION NEWSLETTER
Click on photo for a larger view
January 3, 2001
In the photo above, the beams have been placed for span 5 of the southbound bridge. In the background, the forms are in place for spans 1, 2, and 3. The reinforcing steel will be placed next on top of the forms, then the concrete deck will be poured.
One of the old pier caps is visible in the foreground. From the photo, you can see how much wider the new bridge will be. To remove the old pier cap, the concrete pilings are cut off and the horizontal piece is removed. Then a machine is attached to the pilings, and they are vibrated to loosen them from the soil. Finally the crane removes them to be recycled.
To date, nine of the eleven spans of the old bridge have been removed. Since the old bridge is used as a work platform to construct the new bridge, some of the new construction must be completed prior to demolition of each span.
Additional information will follow as the construction progresses. Should you have any questions, please contact me at (904)677-8740.
Sincerely,
Thomas R. White, PE
Senior Project Engineer