Links: Woodrow Wilson Bridge
Project Home Page - To get
the very latest on the project go to this great site!
Kids Corner
Artist Renderings
Washington
Times Bridge Info Lots of great articles and
more!
Project Updates:
Tiny space is key for big bridge -June 16, 2003
A Pile Load Test Program has
begun and is expected to last through June 2000. April 27, 2000
Environmental tests ruling overturned Dec. 17, 1999
News Updates:
6-21-02
Update
10-22-02 Update
12-14-01
Update
3-22-01 Update
10-20-00 Update
Project Funding News
Sept. 30, 1999
|
PROJECT OVERVIEW:
Quick
Summary
September
23, 2003
Maryland
More
details in Project Overview/Construction Summary on the
Project’s website. Also follow progress on the Project
Scrapbook/Present photo log
Three
construction contracts are underway and nine environmental
mitigation contracts underway.
The
Maryland soils contract has made good progress with one
section in final settlement phase. There are five areas, all
south of the existing Beltway, which are proceeding with the
Stage 2 or Stage 3 lifts. The north side of Rosalie Island is
owned by the National Park Service and is off limits for
construction outside of the MSHA right-of-way due to the habitat
of special animals and birds that are in the area.
The I-295
bridge overpass contract is on target to complete its
northbound and southbound “S-curves” and associated ramps in
Spring 2004.
The second
I-295 interchange contract south of the Beltway, building
the majority of the interchange, has begun many of the bridge
foundations and steel has begun to be placed.
There will be 11 bridges and 6 retaining walls
constructed. Four ramps will be completely built and portions of
four additional ramps will be built. A construction staging area
is adjacent to this site, on the privately owned National Harbor
property, for the in-river superstructure contract.
Environmental
Mitigation contracts
To
compensate for unavoidable impacts within work zones, a
multi-faceted package of mitigation efforts is being carried
out. Many of these
initiatives reach far beyond the Project area, providing
environmental benefits in wide swaths of Virginia, Maryland and
the District of Columbia. Valued
at approximately $50 million, the initiatives include:
Habitat
preservation
- An
84-acre bald eagle sanctuary has been established
Wetland
creation, enhancement or preservation
- More
than 100 acres of wetlands are being created or preserved in
Virginia, Maryland and the District of Columbia
River
grass plantation
- Twenty-two
acres of river grasses are being planted in the lower
Potomac River, serving as fish habitat and cleaning the
water
Reforestation
- More
than 140 acres of woodlands are being planted or preserved
in Prince George's County
Steam
restoration
- "Fish
ladders" enabling spawning fish to cross 25 man-made
barriers will be created on Rock Creek/ Northwest Branch
Rivers in Montgomery and Prince George’s Counties and
Anacostia River (D.C)
- As
many as 15 million herring are being stocked in Rock Creek
and Anacostia River tributaries
- More
than 800-feet of stream bank stabilization in Prince
George’s County
As part of
the environmental mitigation associated with the contract at the
Hunting Point on the Potomac apartment complex, a wetland has
been created. The wetland is adjacent to Hunting Creek, near
Hunting Cove off of S. Washington Street. The environment in the
area is excellent for birdwatching, today, and will be enhanced
with the new wetland. This photo shows the wetland with water.
The wetland is tidal-dependent which means that when the tide is
high there is water in the wetland, as shown. When the tide goes
down, or it is a drier period, this area will seem empty. The
wetland plants clean the water naturally.
Bridge
Three
superstructure contracts are underway. The two approach
contracts are in the process of mobilizing and setting up
casting yards where the segments for the arches will be built
prior to the placement. The contract with the most work on
going, and the most visible, is the movable span contract.
Building an Arch
The first
arch at the drawspan of the new bridge has taken shape. Since
the pedestals were finished, the drawspan contractor has been
building the falsework for
the southernmost support of the arch on the west side of the
drawspan. The falsework is the steel that looks like an
“erector set” that creates a frame for the formwork. The
formwork is the bed of wood on which the concrete will be
placed. Once the rebar has been placed creating the concrete
boxes that lie on the formwork, the concrete will be poured.
Once the concrete has cured, the formwork and falsework will be
stripped away so that you can see the concrete facing. At the
drawspan, there are three arches to support each roadway. For
the other foundations, there will be a pair of arch supports for
both the Inner Loop and the Outer Loop roadways.
Virginia
There are
three construction contracts in Virginia and three environmental
mitigation contracts underway.
The Virginia
soils contract, between US Route 1 and Telegraph Road, is
adding soil on top of the existing ground to load it for bearing
strength. The series of lifts is completed on the Outer Loop
and, in fact, some of the excess material, or surcharge is being
removed since the soil has reached its bearing strength. On the
Inner Loop, additional soil is necessary and some of the areas
will have to settle for a period of time to reach their bearing
strength. In addition, many of the overhead utilities are being
relocated. Currently, Virginia Dominion Power is relocating
transmission towers.
The Virginia
Tie-In contract will join the Wilson Bridge to the US Route
1 interchange. In addition to the roadway work on the Beltway,
which will occur in the future, a lot of work is needed adjacent
to the Beltway. Already, a wetland mitigation site has been
created south of the apartment complex on the west side of S,
Washington Street (see Environmental Mitigation section, this
page). A Washington Street Urban Deck has had its construction
begin with demolition of a part of the S. Washington Street. A
retaining wall is under construction, which will be the southern
edge of the Beltway. Demolition is required and is partially
completed with two buildings down.
One
of the contracts for the Virginia side of the Project is called
the US Route 1 Interchange Advanced Bridge Contract. The
construction of the eleven bridges will be to the south of the
existing Beltway, beyond the Ground Improvement Contract. The
work is not very easy to see by the drivers on the Beltway. That
can be a good thing. This contract will not noticeably affect
the Beltway traffic, as all work will be outside of the roadway,
similar to the Ground Improvement Contract.
11-22-02 Project Overview Update:
- Project corridor is 7.5 miles. Includes
two side-by-side bridges
replacing the old, four rebuilt interchanges, one new access
point in
Virginia, widening the I-95/Capital Beltway and creating an
express/local
lane system as follows:
1. 8 lanes for general purpose traffic
2. 2 lanes for merging/exiting
3. 2 lanes for rail or bus transit or carpool lanes.
These lanes would
not open until connecting systems (rail, bus, HOV) are in place
in Virginia
and Maryland.
- Total estimate is $2.44 billion (due to be updated next
month). Funding
as follows:
1. Special federal funding: $1.631B
2. Virginia: $505M
3. Maryland $292M
4. District of Columbia $15M
Older information
The Woodrow Wilson Bridge Project covers a 5-mile area and is moving forward with
design activities for the bridge and four adjacent interchanges. The bridge, the only
federally owned span on the interstate system, will be doubling is lanes to twelve from
six. The bridge itself will be $600 million out of a total $1.9 billion dollars. The
new bridge will be about 30 feet of the existing bridge and will consist of two 6,000 foot
long mutliple-span bascule bridges. The total width is 257 feet which includes a
fifteen foot gap between them.
The bridge will sit on steel piles 150 feet below the bottom of the river. They
will be supporting 18 v-shaped piers (57 on the existing). The new bridge will add
fifteen more feet in clearance to 70 feet over the existing bridge. By increasing the
clearance the number of draw-span opening will decrease from 220 to about 70.
The original bascule bridge open in 1961 was designed to carry 75,000 vehicles per day,
now it carries over 190,000. A study has shown that if the bridge is not replaced by
2004 it will need to be overhauled or a ban on trucks would be needed.
DESIGN
A unique Bridge Design Competition was completed in November 1998. Its purpose was to
bring forth the finest possible design. Four firms, which submitted a total of seven
concepts, were finalists in the competition. A jury comprised of individuals from a
variety of disciplines, and chaired by former Maryland Governor Harry Hughes, selected a
winning concept which was announced on November 18, 1998 during a press conference.
The winning design is a graceful, seamless concept by Steinman and Deleuw. The
box-girder bridge is characterized by V-shaped piers that offer the look of arches but
enable a more open appearance with smaller foundations than would a true arched design.
The fours team that competed were:
Steinman and DeLeuw (Both part of Parson Corp)
Figg Engineering Group/Johnson &Mirmiran &Thompson Team
HNTB Corp.
T.Y. Lin Internation
FUNDING
Bridge: $600 Million
Ramps and Design: $300 Million
4 large Interchanges in Maryland and Virginia (2 each): $1 billion
As of December 19th, 1999 there is a total of 1.3 billion dedicated to this project. It
breaks down as:
Federal Government: $900 million
Maryland and Virginia: $400 Million ($200 Million each)
Congress is currently being pressured by Clinton and others to come up with the last
$600 million needed to fund this project.
Project Update
10-20-00
Dredging Contract Begins
Because much of the river at the Wilson Bridge is only a few feet deep,
removing soil from the river bottom is needed to create a channel for construction
equipment to safely access locations where the future bridge's foundations will be built.
The first dredging phase will begin this month and end in February 2001. Subsequent
dredging will take place during the same calendar window in succeeding years.
Approximately 300,000 cubic yards of river bottom soil will be removed
this fall/winter. Overall, an estimated 550,000 cubic yards will be dredged during the
course of the entire project. Dredged river soil will be barged to a reclamation site on
the James River east of Richmond, Virginia.
Extensive testing and consultation with environmental agencies have
demonstrated the river-bottom soil to be safe.
The first contract will involve dredging approximately 300,000 CY of material for an
east-west construction channel through a submerged aquatic mitigation (SAV) bed in the
middle of the river. Dredging in open water will only be allowed from October 15 to
February 15 (year-round dredging is permissible from within a cofferdam). It is
anticipated that the dredged material will be barged down the river to the Chesapeake Bay
and then to an upland disposal site. The exact location of this disposal site remains to
be determined.
The second contract will involve the majority of foundations for the bridge as well as
interim site improvements in Jones Point Park, and possibly bulkhead improvements in Jones
Point Park and at the Maryland shore south of the bridge for construction staging areas.
The foundations will likely include steel pipe piles ranging in diameter from 42" to
66" inches for the river piers and Pier V-2, the first pier on the Virginia shore.
The other Virginia piers will likely include 24" square prestressed concrete piles. A
concrete pile cap will also be included in this contract.
The third contract will include the remainder of the construction for the Potomac River
Bridge. This work includes prestressed concrete V-piers, steel box girders, concrete deck,
operator's house, machinery, electrical controls, signing and roadway and aesthetic
lighting. This contract will also include a few foundations that overlap the existing
bridge which would not be accessible in the previous foundation contract.
Potential Construction Quantities Ž VERY PRELIMINARY!
Anticipated Major Quantities:
Bascule Span:
- Steel Pipe Piles: 36,000 LF
- Pile Cap Concrete: 20,000 CY
- Cast in Place Pier Concrete: 30,000 CY
- Structural Steel: 8,000,000 LB
- Epoxy Coated Reinforcement: 700,000 LB
- Reinforcement Steel Bars: 14,000,000 LB
- Post Tensioning Steel Reinforcement: 2,000,000 LB
Approach Spans:
- Prestressed Concrete Pile: 26,000 LF
- Steel Pipe Pile: 120,000 LF
- Pile Cap Concrete: 68,000 CY
- Structural Steel: 75,000,000 LB
- Epoxy Coated Reinforcement: 8,500,000 LB
- Reinforcement Steel Bars: 9,200,000 LB
|
Anticipated Specialty Items:
- Bascule Bridge Operating Machinery
- Bascule Bridge Electrical Controls
- Navigation Lighting
- Bascule Bridge Warning Gates
- Pier Protection System
- Traffic Control Signal System
- Pedestrian Railing
- Bridge Deck Expansion Joints
- Control Tower Building
- Stone Facing Overhead Sign
|
Project Update
3-22-01
CONSTRUCTION OF THE NEW WILSON BRIDGE MOVES FORWARD WITH BID OPENING OF
FOUNDATIONS CONTRACT
Work Anticipated to Start in Late May |
|
Baltimore - The Maryland Department of Transportation's State Highway Administration
(SHA) identified Tidewater Construction Corporation/Kiewit Construction Company/The Clarke
Construction Group, Inc. Joint Venture of Virginia Beach, VA as the apparent winner of the
foundations contract for the new Woodrow Wilson Bridge. Fulfilling a variety of contract
requirements, their bid of $125,396,511 million was the apparent low bid among five
proposals submitted by leading construction firms from across the nation. "This is
another major step forward in the cooperative effort between Maryland, Virginia, and the
Federal Highway Administration to relieve the worst bottleneck on the East Coast"
said Parker F. Williams, SHA Administrator. "The best of the bridge building world
competed for this much-anticipated contract, which guarantees the region's citizens will
receive top value from the contractor." "We are very pleased to win the
work," said E.W. McLaughlin, President of Tidewater Construction Corporation.
"We are also very excited to start work on the project that will soundly support
future generations of bridge travelers." Foundation construction is anticipated to
start in May 2001 and continue until summer 2003. Foundations, consisting of piles that
are driven to support concrete footings and pedestals, will be built for a total of 17
piers (eleven in the river and six in Jones Point Park in Virginia). Built to just above
ground or water levels, the foundations will provide the platforms upon which the
remainder of the bridge will be built.
The remainder of the bridge will be constructed in the third and largest phase of work,
which is estimated to begin in early 2002. This will involve completing the dredging and
building the remainder of the foundations, v-shaped pier supports, steel girders, concrete
deck, roadway barriers and drawbridge operating machinery. Removal of the existing bridge
will also occur during this phase. Subsequent contracts will follow with the ultimate goal
of opening the first new bridge by the end of 2004 and the second new bridge in early
2007. The Project's commitment to minimizing disruption to traffic flow, as well as to the
general public and neighboring communities, will remain a priority throughout the life of
the Project. This pledge to being a "good neighbor" will become evident during
bridge foundation construction. A number of special community-sensitive elements are built
into the foundation job. These include specific times and days for construction, quieter
and more efficient equipment, designated hauling routes and street permit restrictions.
Maximum use of the Potomac River for delivery of materials, supplies and equipment will be
encouraged to avoid community streets. There will be no construction on Sundays and
holidays in Jones Point Park; pile driving hours in the park will be restricted to between
9:00 am and 6:00 pm Monday through Friday and 10:00 am and 4:00 pm Saturday. Pile driving
in the Potomac River is restricted to daylight hours only. Because the initial foundation
work is physically separated from the existing bridge, the driving public should not be
affected. During subsequent construction phases, special efforts will be made to keep
traffic flowing safely and smoothly on the bridge and adjacent interchanges. In addition,
the Potomac River channel in the bridge area should remain open and passable at almost all
times, for both recreational and industrial vessels. |
BID SUMMARY
F.A.P. Yes Thursday, March 22, 2001 12
Noon
CONTRACT # DESCRIPTION
ESTIMATE
PG3415173R FOUNDATION CONSTRUCTION REPLACEMENT
FOR THE WOODROW WILSON BRIDGE
PROJECT.
CONTRACTOR BID AMOUNT
Tidewater Construction
Corporation/
Kiewit Construction Company/
Clark Construction Group, Inc.
$125,396,511.00
Virginia Beach, VA
Pile Foundation Construction Company
$128,480,712.00
New Hyde Park, NY
Jay Cashman, Inc.
$134,122,525.00
Boston, MA
Potomac River Constructors
$134,454,905.00
Cranford, NJ
Modern Continental Construction Company
$187,347,360.00
Cambridge, MA
5-30-01
Maryland and Virginia will share ownership and upkeep of the new Woodrow Wilson Bridge
in an agreement that should guide the region's largest public works project to completion
on schedule, both states' governors said yesterday.
10-22-02
Now Two Years Into Construction,
Project Activity Continues to Step Up
Marking the second anniversary of construction in October,
Woodrow Wilson Bridge Project activity will further accelerate
in the months ahead. Within the next year, seven large
construction contracts are planned to be bid and awarded on the
Mid-Atlantic region’s largest project, joining the five major
contracts that are currently underway or completed More
significantly, the contracts scheduled to be awarded by October
2003 together comprise more than $800 million in estimated value
– more than three times the $240 million in contracts that are
now in progress or already finished.
"The Wilson Bridge Project is the World Series of
transportation construction," commented Parker F. Williams,
administrator of the Maryland State Highway Administration.
"And we’re just rounding first base in terms of
construction activity," added Ronaldo "Nick"
Nicholson, project manager for the Virginia Department of
Transportation. The state agencies, with the Federal Highway
Administration and District of Columbia Department of
Transportation, sponsor the $2.44 billion project.
Ultimately, more than 30 separate contracts are planned for
the 7.5-mile long Wilson Bridge Project, which connects
Virginia, Maryland and the District of Columbia along I-95 on
the Capital Beltway. Coordinating the massive project in a
budget- and schedule-driven manner is essential because several
contractors must work concurrently to meet simultaneous
milestone completion dates. The agencies and their general
engineering consultant (Potomac Crossing Consultants) are making
every effort to enhance timely and responsive coordination with
contractors individually and amongst all contractors
collectively.
Major construction work planned for award in the coming 12
months is detailed below. VDOT and SHA are seeking maximum
competition for the work, which will be advertised in various
trade publications.
Major Construction Work To Be Awarded By
October 2003
Bridge (Maryland State Highway Administration)
Superstructure/Drawbridge (BR-3A)
– Construct the massive piers and movable bascule spans. With
an estimated value of $140-170 million, the contract is planned
for award in the fourth quarter of 2002, with construction
starting in the first quarter of 2003.
Superstructure/Virginia Approach (BR-3B) –
Construct the bridge spans approaching the bascule from the
Virginia abutment. Because the drawspan is located near the
Virginia shore, this approach work is primarily over land. With
an estimated value of $130-160 million, the contract is
scheduled for award in the first quarter of 2003, with
construction following in the second quarter. - more -
Superstructure/Maryland Approach (BR-3C) –
Construct the bridge spans approaching the drawbridge from the
Maryland abutment. This third major component of the new river
crossing involves mainly marine construction work. It is planned
for award in the second quarter of 2003, with construction
following in the third quarter.
The first of the twin bridges is planned for completion in
late 2005/early 2006. After traffic is moved onto the first
bridge, the old bridge will be torn down through demolition
components in each of the above contracts. The second new bridge
is slated for completion in late 2007/early 2008. These key
milestones underscore the imperative of bridge and adjacent
highway work being completed concurrently and on time.
Virginia Landside (Virginia Department of Transportation)
– Align the existing Virginia Beltway and US Route 1
Interchange with the new river bridges that will be south of
the existing bridge. The contract has an estimated value of
$55-65 million and is planned for award in fourth quarter of
2002, with work starting early next year.
US Route 1 Bridges (VA-5) – Construct raised
structures for Beltway and ramps on the southern portion of
the US Route 1 Interchange. With an estimated value of $40-50
million, the contract award is planned for the second quarter
of 2003, with construction commencing in the summer.
US Route 1 Interchange (VA-6) – Rebuild the main
portion of the US Route 1 Interchange. This is the largest
Virginia contract associated with the Wilson Bridge Project,
estimated at $170-200 million, and is planned for award in the
third quarter of 2003, with construction beginning in the
fourth quarter.
Maryland Landside (Maryland State Highway Administration)
I-295 Interchange Southern Ramps and Outer Loop (MA-2&3)
– Align the Maryland Beltway and I-295 Interchange with the
new river bridges, widen the Capital Beltway and provide new
access to a planned major recreation/retail/business development
to the south. This major contract is planned for award in the
fourth quarter of 2002 and to be under construction in first
quarter 2003.
Two Years of Progress
Construction of the new Wilson Bridge started October 19,
2000 with the dredging of a construction channel. During the
following four months, more than 12,000 scoops of river mud –
totaling more than 330,000 cubic yards – were removed and
disposed of in an environmentally beneficial manner.
On July 2, 2001, the first of 1039 piles that will support
the future bridges was driven. The $125 million contract for
building bridge foundations is now 85 percent complete.
Among other advancing construction elements:
- Stabilizing soil conditions in Virginia and Maryland
to support the expansion of the I-95/Capital Beltway is nearly
half finished on both sides of the river.
- Rebuilding ramps and overpasses connecting I-295 with MD
210
is almost halfway completed. This $45 million job
employs more than 100 daily workers.
- Demolition of buildings and garages
that stand in the
path of the new bridge and its highway approaches is now in
progress and will be completed next year.
- Seven environmental mitigation contracts are now underway
in
Virginia, Maryland and the District of Columbia to compensate
for construction impacts, with three more mitigation
contracts to follow. While much of the mitigation work is
being performed at or near the project site, the effort also
extends far and wide, including river grass planting more than
60 miles south where the Potomac River meets the Chesapeake
Bay; wetland creation 30 miles west in Prince William County,
Virginia; woodland planting and preservation 20 miles east in
Prince George’s County, Maryland; and fish passage
restoration 20 miles north in Washington, DC and suburban
Maryland. Substantial habitat preservation work for bald
eagles and other species is also part of the environmental
effort.
6-21-03
Revised schedule as of March 1st, 2003
Contract 2 -
Foundations
Construction Underway |
Superstructure Contract
- Separated into 3 contracts
Contract 3 - Superstructure |
First Contract 3A - Bascule Spans
Contract No. PG3455173R |
Second Contract 3B - VA Approach
Contract No. PG5175173
Construction Underway |
Third Contract 3C - MD Approach
Contract No. PG5155173
Construction Underway |
Maryland Contracts
|
Contract PG3555173 - Pre-Consolidation at
Rosalie Island |
Contract PG3465173 - Ramps E&F at I-295
interchange |
I-295 Outer Loop Local and Express. / National
Harbor Interchange
Contract No. PG 3475173 |
Virginia Contracts
|
Contract K86 - Project No. (FO) 0095-96A-106, C503, D601,
D613 - VA Ground Improvement |
Contract A21 - Project No. 0095-100-104, C510 - VA Tower
Demo
COMPLETED |
Contract A88 - Project No. 0095-96A-106, B648-50, C504,
C51, L802 - VA Tie-In Contract |
Contract A89 - Project No. FO 0095-96A-106, N507 -
Virginia Route 1 Pile Indicator Program
COMPLETED |
Project No. (FO)0095-96A-105,C502, (FO)0095-96A-106,C502 -
Advanced Intelligent Transportation System Installation
Construction Underway |
Contract B69-Project No. (FO)0095-96A-106,C520,B626-629,
B631-634,B640-642 - US Route 1 Advanced Bridge Contract
NTP June 15, 2003
Environmental Mitigation |
MSHA - Contract No. AT1355173 - Fish Passage (MM1)
Under Construction |
MSHA - Contract No. 3445173 - Northwest Branch / Sligo
Creek (MM2)
Under Construction |
MSHA - Contract No. PG3525173 - Cabin Branch / Tuxedo Road
(MM4)
Restart Spring 2003 |
MSHA - Contract No. SM8085173 - Submerged Aquatic
Vegetation (MM7)
Initial Phase Completed
Restart Spring 2003 |
MSHA - Contract No. PG5015173 - Reforestation at various
WSSC sites (MM8)
Initial Phase Completed
Restart Spring 2003 |
MSHA - Contract No. PG51351173 - Offsite Reforestation
(MM9)
Under Construction |
VDOT - Virginia Shoreline Stabilization Contract
Contract L13 - Project No. 0095-96A-106, L801 (VM1)
Completed |
VDOT - Four Mile Run / Hart Property Wetland Mitigation
(VM2)
Contract A20-0095-100-104, L802
Under Construction |
VDOT - Submerged Aquatic Vegetation (VM4)
Contract A52-0095-100-104, L803
Initial Phase Completed
Restart October 2003 |
MSHA - Contract No. AT1345173 - Rock Creek (MM3)
Advertise April 8, 2003
Bids Open July 3, 2003 |
MSHA - Contract No. PG3525173 - Bladensburg Marina (MM5)
Advertised March 28, 2003
Bids Opened April 29, 2003 |
VDOT - Silver Property / Aquira Harbor (VM3)
Contract A19-0095-100-104, L801
Advertise May 13, 2003
Bids Due June 24, 2003 |
|
|