17th Street Causeway Bridge Project

December 99' Project Update

 


Date of Report:12/99

information provided by FDOT

IDENTIFICATION
Project No.: 227874-1-52-01 Highway No.: SR A-1-A Construction Project Manager: Gregory Lady Phone: (954)524-9189
Feature Intersected: Intracoastal Waterway Construction Engineering Inspection Consultant: Parsons Brinckerhoff Construction Services
Description: 17th Street Causeway Bridge Replacement Project Prime Contractor: Traylor Brothers Inc. Designer: E. C. Driver and Associates, Inc.

TIME

Start Date: 09/27/97 Season Complete: Winter 2001 Elapsed Time(ET) in days: 729 Current Total Duration (CTD) in days: 1050 Percent Elapsed Time (ET/CTD x 100): 69.4%

PROGRESS

Earnings To Date (E): $42,651,987.94 Current Total Cost (CTC): $ 65,543,162.72 Percent Actual Progress (E /CTC x 100): 65.1%

WORK THAT IS FINISHED OR UNDERWAY

North bridge segmental erection complete. Bascule piers and leaves complete; exodermic decks poured CIP walls complete. Electrical and mechanical work underway to make bridge operational. Deck grinding, railings, and construction of roadway approaches also underway.

UP COMING WORK

Complete electrical & mechanical work on bascule piers. Finish roadway approaches for North bridge and miscellaneous work on segmental bridge approaches (railings, lighting, etc.).

 

 

17th Street Causeway Bridge Project

December 99' Project Update

 


Date of Report:12/99

information provided by FDOT

IDENTIFICATION
Project No.: 227874-1-52-01 Highway No.: SR A-1-A Construction Project Manager: Gregory Lady Phone: (954)524-9189
Feature Intersected: Intracoastal Waterway Construction Engineering Inspection Consultant: Parsons Brinckerhoff Construction Services
Description: 17th Street Causeway Bridge Replacement Project Prime Contractor: Traylor Brothers Inc. Designer: E. C. Driver and Associates, Inc.

TIME

Start Date: 09/27/97 Season Complete: Winter 2001 Elapsed Time(ET) in days: 729 Current Total Duration (CTD) in days: 1050 Percent Elapsed Time (ET/CTD x 100): 69.4%

PROGRESS

Earnings To Date (E): $42,651,987.94 Current Total Cost (CTC): $ 65,543,162.72 Percent Actual Progress (E /CTC x 100): 65.1%

WORK THAT IS FINISHED OR UNDERWAY

North bridge segmental erection complete. Bascule piers and leaves complete; exodermic decks poured CIP walls complete. Electrical and mechanical work underway to make bridge operational. Deck grinding, railings, and construction of roadway approaches also underway.

UP COMING WORK

Complete electrical & mechanical work on bascule piers. Finish roadway approaches for North bridge and miscellaneous work on segmental bridge approaches (railings, lighting, etc.).