A1A Resurfacing
Construction Schedule

Items in red are completed.

 

Start date Complete
Project Start April 3, 2000  
Clearing and Grubbing and Drainage Work April 3, 2000 April 28, 2000
Excavation April 24, 2000 July 18, 2000
Shoulders (1.5M paved shoulder) (night) April 30, 2000 May 5, 2000
Milling and Paving of A1A (night) May 17, 2000 June 4, 2000
Friction Course (Finish Layer) (night) June 19,2000 July 20, 2000
Misc, Punchlist June 26, 2000 Aug 15, 2000
Project Completion   Aug 18 2000 *
* Completion Date can be extended for bad weather.